Project goal: to establish industrial production of glyphosphate, caustic soda, trichloride phosphorus and calcium chloride in the Republic of Kazakhstan.
The goal of the Formulation Complex production and sale of plant protection products (herbicides) using advanced technologies for the Kazakhstan market.
Production capacity: 2,919,708 litres of liquid glyphosate containing herbicide and 1000 tons of granulated glyphosate containing herbicide per year.
The Formulation Complex was commissioned in January 2019.
Place of project implementation: Chemical Park Taraz Special Economic Zone.
Owners structure:
Detailed information on the website: www.chemplus.kz
Construction of the first integrated gas chemical complex in Atyrau region (Phase I – polypropylene production)
Project goal: Construction of a plant to produce 500 thousand tons of polypropylene per year.
Production capacity: 500 thousand tons of polypropylene
Place of project implementation: Atyrau region, territory of SEZ NIPT.
Feedstock: propane
Number of jobs: 500 permanent and 4000 temporary jobs
Share in the capital: Samruk-Kazyna Ondeu LLP (49.5%); NC KazMunayGas JSC (49.5%); Almex Plus (1%)
Current status and future plans: construction and installation works are underway, the project has been transferred to the trust management of NC “Kazmunaigas” JCS.
Current status:
Construction of infrastructure facilities on the territory of SEZ National Industrial Petrochemical Technopark (SEZ NIPT)
Project goal: To provide the participants of SEZ NIPT with the necessary infrastructure.
Production capacity:
Share in capital:
Place of project implementation: Atyrau region, territory of SEZ NIPT, site Karabatan.
Feedstock: fuel gas, raw water
Number of jobs:about 900 during construction and 300 during operation.
Current status and future plans: GTPP is in the final stage of construction (progress – 97%), commissioning is planned for 1st quarter of 2020. GP development of the DED is being completed, works of the 0 cycle are in progress. Construction is planned to be completed in 2021. 220 kV overhead power line and substation – the facility has been put into operation. Engineering networks – design has been completed, construction works are in progress. Completion of construction is planned in 2021.
Current status:
Overall progress is 95.23%.
1. Under the GTPP project:
2. Under the WT project:
Project goal: Reconstruction of the sulfuric acid plant in Akmola region
Production capacity: 180 thousand tons of sulfuric acid per year
Commissioning of the project: 2015
Main raw materials for production: granulated sulfur supplied by Tengizchevroil LLP
Main consumers of products: uranium mining enterprises of the Republic of Kazakhstan.
Number of permanent jobs: 230 people
Detailed information on the website: www.ssap.kz
Owners structure:
The project is part of the State Program for Boosted Industrial and Innovative Development of the Republic of Kazakhstan for 2010-2014, the Program for Development of Chemical Industry of the Republic of Kazakhstan for 2010-2014, as well as the map of industrialization of the region.
The plant is fully automated, equipped with modern equipment and environmentally friendly (all operations are performed in closed mode).